Transportation Secretary Sean Duffy stated on Sunday that the Federal Aviation Administration (FAA) must reconsider the timing of its infrastructure upgrades. This follows a daytime maintenance at a remote facility that led to a nationwide ground stop, affecting air travel extensively.
During an appearance on CBS News’ Face the Nation, Duffy noted that while major facility maintenance is usually scheduled overnight, work at remote sites has not adhered to this rule due to previously low-risk assessments. “Clearly, as we observed on Friday, this was not the case,” he mentioned. “The network was overwhelmed, necessitating an unprecedented measure of issuing a ground stop.”
He further commented, “We now need to reassess our scheduling for such operations.”
The affected remote facility is located in El Dorado, Arkansas, where FAA telecommunications contractor L3Harris Technologies was working. They were replacing an outdated copper communications line with a fiber line when the disruption occurred.
Duffy explained that the upgrade was mandated by the telecom provider, stating, “We were compelled to switch from copper to fiber because of the telecommunications provider’s restrictions, and during that process, network flooding occurred.”
The investigation, involving the FAA, L3Harris, and receiving FBI support, is examining the reasons a router began excessive data broadcasting and similar issues noted in another location in Amarillo, Texas. No malicious activity has been identified, while 69 routers have been temporarily disabled nationwide as a safeguard.
Responding to whether the incident could have been foreseen, Duffy defended the FAA’s risk assessment processes, stating, “Our procedures have included similar installations countless times without issue.” The cause of the issue, whether due to the L3Harris installation or the routers themselves, remains under investigation, with results to be shared publicly.
Renewed Scrutiny on Modernization Efforts
The event has reignited focus on a Government Accountability Office (GAO) report from last September. The report criticized the FAA’s modernization efforts, labeling their pace as excessively fast and potentially hazardous to air traffic control.
The GAO highlighted the absence of a unified lifecycle cost estimate and a comprehensive master schedule for the initiative. The FAA’s segmented approach of 11,389 individual project schedules, not sufficiently integrated, risks overlap, and inefficient impacts on air traffic control operations.
Coordination issues, as noted by the GAO, threaten the delay of retiring outdated systems and may cause additional air traffic disruptions.
Scale of Upgrades and Funding
The El Dorado operation signifies part of a broader modernization initiative focused on updating telecommunications, radar, radio, and weather infrastructures. According to Duffy, 70% of the FAA’s copper connections have been converted to fiber, a significant jump from the 2,560 to 5,170 reported to be completed as of May 2026. He also mentioned the transition of nearly 470 radios to new systems.
The endeavor is backed by Congress’ allocation of $12.5 billion in July 2025 for the Brand New Air Traffic Control System (BNATC) modernization’s first phase, ending in December 2028. The second phase, aimed at advanced automation, projects a requirement of $10.2 billion. However, its timeline remains undetermined.
On Sunday, Duffy expressed plans to secure $50 billion overall for the entire modernization effort, highlighting the challenge and investment of sourcing new air traffic control equipment. “It’s not a matter of buying commercial radar,” he clarified. “This is a complex and substantial endeavor.”
Acknowledging the complexity and scale of the required upgrades, Duffy remarked, “This overhaul is decades overdue. It’s been neglected because of its complexity.”
For comments on this story, contact Newsweek editors Steve Mollman and Anthony Murray.