Last quarter, Microsoft spent $5 billion less than expected on artificial intelligence infrastructure, as revealed in their quarterly earnings call. Chief Financial Officer Amy Hood attributed the reduced expenditure to delays from third-party cloud providers. Consequently, Microsoft adjusted its annual capital expenditure forecast by $5 billion.
These developments caused a decline in neocloud stock prices, raising doubts about the capability of these emerging companies to meet their multi-billion-dollar commitments. Although Microsoft did not specify which providers were responsible, satellite analysis from Aterio suggested the involvement of two neocloud companies: Iren and Nebius.
Data Center Delays
In Texas, Iren is constructing four data centers for Microsoft under a $9.7 billion agreement. A recent satellite image from October 21 showed that one of these centers, Horizon 4, lacked backup power generators and cooling equipment. This insufficiency risks delaying its scheduled completion by the year’s end. Earlier, Iren reported that shortages affected the delivery of Horizon 1, accepted by Microsoft in August.
Additionally, DataOne is working on a project in New Jersey for Nebius, part of a $17.4 billion deal. Aterio reported that around 140 megawatts of the project’s planned capacity might not be operational until 2027. The project faced permit issues for its power generators, worsened by a transition to fuel cells. As a result, regulators fined DataOne $1 million for operating without permits in September.
Broader Challenges
The potential setbacks highlight ongoing difficulties. Microsoft recently ended a contract with Nscale, another neocloud company, due to power supply delays. According to Currence, between 30% and 50% of data center capacity initially planned for this year could be postponed until 2027 or later, owing to electricity shortages and construction challenges.
A Microsoft representative stated their infrastructure strategy combines flexibility and choice, using their own data centers along with leased facilities and third-party providers. Iren and DataOne chose not to comment, while Nebius did not respond to requests for remarks.